Exam Cheat Sheet · Quick Reference

Alabama - Carpentry and Framing Contractor

Alabama  ·  PSI Services Contractor

Verified, not estimated. Every figure below is drawn from the official exam structure we maintain — question counts, passing standard and topic weighting. Practice questions are grounded in the source law with statute citations. We omit any figure we can't verify rather than guess at it.
Total questions
60
Passing score
70%
Exam time
180 min
Administered by
PSI Services Contractor
Format
Reference materials allowed

Alabama State Portion 60 questions

Estimating and Plan Reading 9 Q · 15%
Reading and interpreting span tables for headers, girders, joists, and raftersCalculating board feet of lumber from nominal dimensionsEstimating quantities of framing materials for walls, floors, and roofsReading architectural plan views, elevations, and section viewsInterpreting architectural symbols, abbreviations, and drawing conventionsUsing scale drawings and architect's scale for measurementsUnderstanding schedules and specifications in a plan setTypes of cost estimates including pre-design, quantity takeoff, and unit-cost methods
Layout 7 Q · 12%
Site layout methods using reference lines and surveying instrumentsTypes of surveying instruments (builder's level, transit, theodolite, laser level, GPS)Setting up and leveling a transit or level over a station markLaying out right angles and simple rectangles using a level or transitSetting up batter boards to establish building outlineEstablishing grades and measuring differences in elevation using differential levelingCalculating excavation volume in cubic yardsSoil bearing capacity, porosity, and overdig considerations
Walls 14 Q · 23%
Wood wall framing stud size, height, and spacing requirementsWall bracing methods and braced wall panel constructionHeader and girder spans for wall openingsFastening schedules for wall framing connectionsDrilling and notching limitations for studs and top platesWall anchorage to foundations and seismic requirementsCold-formed steel wall framing member sizing and connectionsCripple wall construction and bracing requirements
Floors and Stairs 13 Q · 22%
Floor framing components: posts, girders, sill plates, joists, and subfloorFloor joist span tables and allowable spans by species, grade, and spacingSubfloor installation: panel sheathing types, fastening schedules, and glue-nailingSpecial floor framing conditions: openings, bearing walls, cantilevers, and bathroom framingStair terminology and parts: treads, risers, stringers, handrails, and balustersStair code requirements: riser height, tread depth, headroom, width, and baluster spacingStringer layout and construction: cut-stringer, cleat-stringer, and housed-stringer methodsCutting, notching, and drilling restrictions for floor joists
Roofs 12 Q · 20%
Rafter sizing and span tables for wood roof framingRidge board and ridge beam requirementsRoof framing members: collar ties, purlins, braces, and ceiling joistsRoof sheathing materials and installationRoof covering types and minimum slope requirementsRoof ventilation and attic access requirementsRoof drainage, flashing, and weather protectionRoof truss design, bracing, and installation
OSHA Safety 5 Q · 8%
Fall protection requirements and systems (guardrail, safety net, personal fall arrest)OSHA employer and employee rights, responsibilities, and general safety provisionsPersonal protective equipment (PPE) selection, use, and employer obligationsHand tool and power tool safety requirementsLadder and stairway safety requirementsHazard communication and hazardous materials on construction sitesFire protection and prevention on construction sitesFirst aid, medical services, and emergency action plans

Key Distinctions

Nominal dimensionsvsActual (net) dimensions

Nominal dimensions (e.g., 2×4) are the named size used for specifying lumber on drawings and board-foot calculations, while actual/net dimensions (e.g., 1½"×3½") are the true dressed size required for engineering computations.

2021 International Building Code, Section 2301.2
Quantity takeoff estimatevsPre-design (parametric/rough) estimate

A quantity takeoff is prepared from completed construction documents using actual counts and measurements, while a pre-design estimate is a rough approximation made before drawings are finished, often using historical cost-per-unit data.

IRC, Section R602.3, Table R602.3(1)
Underlayment position at eavesvsUnderlayment position at rake edges

At eaves the underlayment is installed OVER the drip edge, while at rake edges the drip edge is installed OVER the underlayment.

IBC Section 1507.2.8.3
Plan viewvsSection/elevation view

A plan view looks straight down from above (used for floor plans, roof framing layouts, and site plans), while a section or elevation view looks horizontally to show heights and vertical relationships.

Carpentry and Building Construction, Section 17.1, Page 469
Floor joists resting on top of girdervsFloor joists framing into the side of a girder

Joists resting on top of a girder bear directly on it, while joists framing into the side must be supported by approved framing anchors or ledger strips of at least nominal 2×2.

Section R502.6.2
Rafter span (horizontal projection)vsActual rafter length

Rafter spans in IRC span tables are measured along the horizontal projection of the rafter, not along the sloped actual rafter length.

IRC, Section R802.4.1
Unit-cost estimatevsBoard-foot estimate

A unit-cost estimate divides the building into components measured in lineal feet (walls) or square feet (floors/roofs) and applies a cost per unit, while a board-foot estimate counts individual pieces using nominal dimensions to find total lumber volume.

Carpentry and Building Construction, Section 2.4, Pages 61-62
TheodolitevsBuilder's level

A theodolite reads both horizontal and vertical angles electronically with an LCD display for high-accuracy work, while a builder's level establishes elevations and horizontal sightings but does not electronically display angle measurements.

NASCLA/Carpentry Reference, Chapter 9 — Types of Instruments
Differential levelingvsSingle-setup leveling

Differential leveling is used when points are remote from each other and require one or more intermediate instrument setups, while single-setup leveling determines elevation differences from one instrument position.

NASCLA/Carpentry Reference, Chapter 9 — Measuring a Difference in Elevation
Window/door schedulevsRoom-finish schedule

A window/door schedule is a chart providing rough-opening sizes and window/door designations, while a room-finish schedule identifies the floor, wall, and ceiling materials and finishes for each room.

Carpentry and Building Construction, Section 16.2, Page 440
Rafter span adjustment factor (Hc/Hr = 1/3)vsStandard (unadjusted) rafter span

When ceiling joists or rafter ties are located at one-third the ridge height above the support walls, a factor of 0.67 must be applied to reduce the tabulated rafter span, reflecting the increased outward thrust on bearing walls.

IRC, Table R802.4.1(9)
Batter boardsvsReference line

Batter boards are temporary wood structures set at least 4 feet beyond each foundation corner to hold layout strings, while a reference line is an existing feature (street, property line) from which measurements are taken without a surveying instrument.

NASCLA/Carpentry Reference, Chapter 9 — Setting Up Batter Boards

Key Terms

Nominal dimensions (IBC Section 2301.2) 2021 International Building Code, Section 2301.2
Per IBC Section 2301.2, lumber dimensions on construction documents are deemed nominal unless specifically designated as actual dimensions.
Net (actual) dimensions for computations (IBC Section 2304.2) 2021 International Building Code, Section 2304.2
Per IBC Section 2304.2, structural computations for wood members must use net (actual) dimensions, not nominal sizes.
Truss design drawing requirements (IBC Section 2303.4.1.1) 2021 International Building Code, Section 2303.4.1.1
Per IBC Section 2303.4.1.1, each truss design drawing must include at minimum the slope or depth, span, spacing, joint locations, support locations, number of plies, bearing widths, and design loads.
Wood structural panel identification (IBC Section 2303.1.5) 2021 International Building Code, Section 2303.1.5
Per IBC Section 2303.1.5, each wood structural panel must bear an approved agency trademark showing grade, bond classification, and Performance Category.
Construction document structural requirements (IBC Section 1603.1) 2021 International Building Code, Section 1603.1
Per IBC Section 1603.1, construction documents must show the size, section, and relative locations of structural members with floor levels, column centers, and offsets dimensioned.
Wind speed disclosure for light-frame buildings (IBC Section 1603.1 Exception) 2021 International Building Code, Section 1603.1 Exception
Per IBC Section 1603.1 Exception, construction documents for conventional light-frame buildings must indicate the basic design wind speed and wind exposure category.
Stair riser/tread tolerance (IRC Sections R311.7.5.1 and R311.7.5.2) Sections R311.7.5.1 and R311.7.5.2
Per IRC Sections R311.7.5.1 and R311.7.5.2, within any single flight of stairs the greatest riser height and greatest tread depth must not exceed the smallest by more than ⅜ inch.
Footing width adjustment for wide buildings (IRC Table R403.1(1) footnote c) IRC, Table R403.1(1), footnote (c)
Per IRC Table R403.1(1) footnote (c), when building width exceeds 32 feet, footing width increases by 2 inches and footing depth increases by 1 inch for every 4 feet of additional width.
Board foot IRC, Section R602.1, R602.3
A unit of lumber volume calculated as (nominal thickness in inches × nominal width in inches × length in feet) ÷ 12, always using nominal dimensions.
Quantity takeoff estimate IRC, Section R602.3, Table R602.3(1)
An estimate prepared from completed construction documents by counting and measuring actual quantities of materials shown on the plans.
Span table Carpentry and Building Construction, Section 13.2, Page 355
A list of distances that a particular structural product can span between supports such as walls or columns, organized by species, grade, and spacing.
Differential leveling NASCLA/Carpentry Reference, Chapter 9 — Measuring a Difference in Elevation
The process of determining elevation differences between remote points by using one or more intermediate instrument setups.
Porosity NASCLA/Carpentry Reference, Chapter 9 — The Excavation
The measurement of the ability of water to flow through soil, used to evaluate drainage conditions before foundation excavation.
3-4-5 rule Carpentry and Building Construction, Section 16.2, Pages 438-439
A field squaring method in which measuring 3 feet along one wall line and 4 feet along a perpendicular produces a diagonal of exactly 5 feet if the corner is square.
Presumptive load-bearing value (IRC Table R401.4.1) IRC, Table R401.4.1
Per IRC Table R401.4.1, sandy gravel/gravel soils (GW and GP) carry a presumptive load-bearing pressure of 3,000 psf, used to size footings prescriptively.
HDR (architectural abbreviation) Carpentry and Building Construction, Ready Reference Appendix, Page 1024
Standard architectural abbreviation for 'Header,' as listed in the architectural abbreviations reference.

Formulas to Know

Board feet of lumberBoard feet = (Nominal thickness in. × Nominal width in. × Length ft) ÷ 12
Excavation volume (cubic feet to cubic yards)Volume (cu yd) = (Length ft × Width ft × Depth ft) ÷ 27
Excavation dimensions with clearanceExcavation length = Building length + (clearance × 2); Excavation width = Building width + (clearance × 2)
Scale drawing conversionActual length = Drawing measurement ÷ Scale factor [e.g., at ¼"=1'-0": Actual ft = Drawing inches ÷ 0.25]
Stud count for wall (16" OC)Number of studs = (Wall length ft ÷ 1.333) + 1
Floor area (for rough material estimate)Floor area (sq ft) = Length ft × Width ft
Roof sheathing panels with wastePanels needed = (Roof area ÷ 32) × 1.05 [adds 5% for trim and waste]
Adjusted rafter span (raised rafter ties)Adjusted span = Tabulated span × Adjustment factor [e.g., × 0.67 when Hc/Hr = 1/3]